Work performedEjector pump installPVC branch reconnectBasin lid securePump test
DateMay 20, 2026
We removed the basin lid and the old ejector pump, then installed a new ejector pump. We cut the three PVC branches, reconnected them, and secured the basin lid. We then tested the pump. View technician’s notes
1. Cut all three pvc branches
2. Remove basin lid
3. Remove ejector pump
4. Install new ejector pump
5. Reconnect branches
6. Secure basin lid
7. Reconnect pvc branches
8. Test pump
Warranty
2 years parts and labor